Hello Renjith,
In fact this is the thing people rarely notice / show interest including me. My understanding is as under:.
- Below we are talking with respect to one Equipment. And my understanding (not very well studied)
- Processing days obviously is the days the Notifications took. It is the time period between Required start ,Required End (M3) or Malfunction Start and Malfunction End (M3).
- If in some Notifications the End dates are left blank or forgotten, the Processing days will be going on adding.
- If might remove the overlaps in the Duration found if any in any Notifications.
- Processing days is a field of S061 info structure and is a part of report MCI3.
- You can run that report for a period and drilldown to Equipment levels and have the value of this field for an Equipment and then compare it with the Notification durations in IW28.
Good luck
KJogeswaraRao