Dear Gurus,
I want to select alternative BOM while creating the subcontracting PR but system is picking automatically 1st BOM from system. Is there any customization is required or master data.
Detail Information
Header Material - Printed Fabric
BOM 1 - Dyed Fabric A
BOM 2 - Dyed Fabric B
Now I have to create Subcontracting PR for Printed Fabric Material and before assigning the component system is not asking the BOM option.It is considering automatically 1st BOM.
Here i have maintain the 2 production version for header material and even i have assign the selection parameter 3 in master data MRP4 view. Even if i will maintain subcontracting info record and maintain production version that will also impact with vendor combination only and PR vendor is not required.
Kindly let me know is there any standard option is available for PR.
Thanks&Regard,
Dhruv.